Tuzla Factory Construction
It was established on a plot of 2500 m². Bored piles are driven on three sides, and the floor height is 8 m. Basement floor curtains are made with a single face formwork system. In the factory building with a total closed area of 5500 m², 8150 m³ of concrete, 1300 tons of iron and 16100 m² of formwork, and in the 8 mt storey building with 38500 m³ of formwork scaffolding, the manufacturing was completed in 11 months with an average team of 30 people.
| DETAIL | |
|---|---|
| Employer | Alpa Makina San. Tic. Ltd. Şti. |
| Time of work | November 2014/September 2015 |